Skip to main content

Extension of screw piles: when and how to increase the pile length

At first glance, it seems that the pile length calculated in the design should always be sufficient. But in practice, things are a little different. Soil is a capricious material: in one place it's dense loam, while two meters away it's quicksand or peat. Therefore, when driving the pile, you have to adapt to the actual situation.

The main reasons for extending piles are:

1.       Not reaching the solid soil layer. When driving, the operator feels that the pile still moves easily, indicating that there is no supporting layer yet. If left untreated, the foundation may "wander" or settle.

2.       Elevation differences on the site. On slopes, lower piles must be longer to ensure the foundation pad is level.

3.       Drilling or calculation errors. Sometimes the designer failed to take into account soil characteristics, or site conditions have changed due to rain, backfill, or machinery use.

4.       A heavier structure is planned. If the design has changed (for example, brick walls have been chosen instead of frame walls), the supporting piles must be deepened and reinforced.

5.       Replacing old piles or repairing the foundation. During reconstruction, it is often necessary to reach a more stable horizon, in which case the piles are also extended.

Screw Pile Extension Methods

Pile extension can be accomplished in various ways, but the goal of all methods is the same: to ensure a strong, watertight, and coaxial connection between the main pile and the extension. This directly affects whether the foundation can withstand the design load.

There are two main methods:

1. Welded connection

This is the most common option. A metal sleeve or extension pipe of a suitable diameter is welded to the end of the pile.

Pros:

        High connection strength;

        Sealed joint;

        Suitable for piles of any diameter.

Cons:

        Requires an experienced welder;

        Misalignment may cause distortion, especially when screwing deeply.

To avoid errors, the pile is leveled before welding, and the seam is welded all the way around with a continuous weld. After this, the joint is coated with an anti-corrosion coating—usually a bitumen mastic or zinc-based primer.

2. Bolted connection (on a sleeve)

This is used when welding on-site is not possible—for example, near a house or in subzero temperatures. The extension pipe is inserted into the sleeve and secured with bolts.

 Pros:

        Installation is possible even in hard-to-reach places;

        Easy to remove if necessary.

Cons:

        Less rigidity of the connection;

        Requires regular inspection and tightening of bolts.

How the extension process is performed - step by step

Step 1. Determining the Need for Extension

While screwing, the operator feels resistance. If there is no resistance, it means the solid layer has not yet been reached. The pile is driven deeper than planned, and the decision is made to extend it.

Step 2. Preparing the Pile End

The end of the pipe is cleaned of dirt and soil, and the cut is checked for evenness. This is necessary to ensure the extension fits snugly and without gaps.

Step 3. Installing the Extension

An extension—a section of pipe of the same diameter and wall thickness—is either pushed or inserted onto the pipe. The length depends on how far the pile is from the solid layer, typically 0.5–2 meters.

Step 4. Connection—Welded or Bolted

        For welding, the connection is welded all around, using a continuous weld.

        For a bolted connection, the coupling is secured with 2–4 bolts.

After this, the connection is checked for alignment using a level or template. Step 5. Corrosion Protection

The connection is coated with an anti-corrosion compound—most often, cold galvanizing or bitumen mastic. For more reliable protection, apply two coats, drying between them.

Step 6. Continued Screwing

The pile with the extension is screwed in to the design level. If the pile still slides easily, the screwing process is repeated. Sometimes, two or even three sections must be made, especially on soft or marshy soils.

Mistakes when installing screw piles and how to avoid them

1. Misalignment during welding

The most common mistake is welding the extension at a slight angle. Visually, this is almost imperceptible, but as the pile is tightened further, it arcs. As a result, the pile heads are at different levels, and the foundation is at an angle.

How to avoid: Use a spirit level and a template to align the axes. On-site, professional installers check the vertical alignment immediately after each tack weld before welding the entire seam.

2. Incomplete or uneven weld

Some "experts" save time and metal by welding only half the circumference. This results in microcracks appearing in the joint, and after a couple of years, the pile may simply crack.

How to avoid: The weld should be continuous all the way around, without gaps or overlaps. After cooling, clean the weld and coat it with an anti-corrosion mastic.

3. Using a pipe of a different diameter

When there's no suitable extension, some people decide to "use whatever's available." This is a serious mistake: the load is distributed unevenly, the pipe begins to play, and over time, it can bend.

How to avoid: The extension must be exactly the same diameter and wall thickness as the pile. Check the match down to the millimeter.

4. Lack of anti-corrosion treatment

If the metal is left unprotected after welding, corrosion will appear within a season. This is especially dangerous for the joint, where rust weakens the metal most quickly.

How to avoid: After welding, immediately clean, prime, and apply a protective layer. For bolted connections, additionally treat the areas around the bolts.

5. Incorrectly selected extension length

Too short will not reach the solid layer; too long will make screwing difficult and increase the stress on the joint.

How to avoid: Use actual soil conditions as a guide. If you are not sure, do a test screwing before ordering the entire set of piles.

Comments

Popular posts from this blog

4 REASONS NOT TO DRIVE SCREW PILES YOURSELF

Screw piles are suitable for constructing piers and docks, terraces, gazebos, bathhouses, and utility buildings. They have sufficient load-bearing capacity for frame and wooden residential buildings. And most importantly, they can be installed independently! No preliminary excavation work or heavy construction equipment required. However, installation work requires adherence to technical regulations; failure to follow these regulations will reduce the stability, safety, and service life of the foundation. TOP MOST COMMON MISTAKES made by amateurs when installing screw pile foundations: 1. FORGETTING ABOUT SOIL SURVEY Without a comprehensive geological survey, it is impossible to calculate the optimal pile driving depth. To perform its function of transferring loads to soil layers with sufficient bearing capacity, a helical pile's blades must reach dense rock and penetrate the winter soil freezing level. If the bottom of the pile becomes suspended in loose or water-saturat...

Mechanized installation of screw piles

  Advantages of Mechanized Screw Pile Installation When it comes to screw piles, precision and uniform penetration are paramount. Level errors or vertical misalignment can later result in crooked piping or a loose floor. This is why mechanized installation produces results that cannot be replicated manually. 1. Vertical and Depth Accuracy Modern hydraulic installations allow torque and screw direction to be controlled with an accuracy of fractions of a degree. The operator can see everything using the level and equipment readings. While manual piles often wander vertically, especially in dense soils, specialized equipment drives them precisely along the axis—without deviation or distortion. 2. High Installation Speed A team using mechanized installation can install up to 40–60 piles per day, compared to 10–15 with manual installation. For example, the foundation for a 100 m² frame house can be built in half a day. At the same time, quality is not compromised: the mach...